  1. Height of water pressure head, h = 300 m
    Volume of water flow per second, V = 100 m3/s
    Efficiency of turbine generator, n = 60% = 0.6
    Acceleration due to gravity, g = 9.8 m/s2
    Density of water, ρ = 103 kg/m3
    Electric power available from the plant = η x hρgV
    = 0.6 x 300 x 103 x 9.8 x 100 = 176.4 x 106 W = 176.4 MW