A contractor estimates that 3 persons could rewire Jasminder’s house in 4 days. If, he uses 4 persons instead of three, how long should they take to complete the job?

  • 8

NCERT Solutions for Class 8 Mathematics Chapter 13
Important NCERT Questions
Direct and Inverse Proportions Chapter 8 Exercise 13.2
NCERT Books for Session 2022-2023
CBSE Board
Questions No: 6

Share

1 Answer

  1. Let time taken to complete the job be x.
    Persons 3 4
    Days 4 x
    Here the number of persons and the number of days are in inverse proportion.
    ∴ 3/4 = x/4 ⇒ 4Xx=3×4 ⇒ x=3×4/4= 3days
    Hence, they will complete the job in 3 days.